11/26/0427

Scout Moor Wind Farm Rochdale

Pending

Observations to Neighbouring LPA: Construction and operation of 12 wind turbines with a maximum height to the tip of the blade of 180 metres (above ground level), together with associated ancillary infrastructure comprising crane pads and hardstandings; new access tracks; improvement and widening works to Scout Road; onsite substation; underground electrical infrastructure and cabling; fencing and boundary treatments; external lighting; drainage infrastructure; habitat and moorland restoration works; public right of way works; landscaping; temporary construction compound and staging area; underground electrical grid connection to the Rossendale Bulk Supply Point; and associated engineering works; alongside the retention of and improvements to existing access tracks associated with the existing Scout Moor Wind Farm.

Type
Planning
Submitted
17 Sep 2026
View on council portal →